A broad river flows past wooded banks, homes, and floating docks.

The Last Gap in Lake Oswego's River Path Took Nearly Two Decades of Easements, and Construction Needs Just One Season

November 5, 2026

"We can't just get that property and sit on it forever," Mayor Joe Buck told the City Council on March 31, according to the Lake Oswego Review. That night the council voted unanimously to fund the missing piece of the Willamette River Greenway Trail between George Rogers Park and the existing path at the Willamette condos.

The property he meant had taken the city years to secure. The trail itself is about 870 feet of new pathway, Project Manager Kyra Haggart told the council. Once it's done, Lake Oswego will have a continuous 2.25-mile path along its Willamette riverside. Construction began this summer and is now in its last weeks. Most of the wait came before that, and most of it was about land.

Five properties stood in the way

Before any concrete was poured, the city needed legal access across five private properties between George Rogers Park and the southern end of the existing trail. The Review reports that Parks and Recreation began getting pathway easements in 2007 and secured three of the five over time. In 2023 the city condemned the remaining two to obtain easement rights.

After that, the project moved quickly. The City of Lake Oswego's project page logs each step.

  1. 2007: Parks and Recreation begins getting pathway easements.
  2. 2023: The city condemns the last two properties for easement rights.
  3. March 31, 2026: Council approves $1.76 million in funding.
  4. April 28, 2026: The city receives 10 construction bids and names Daybreak Construction the successful bidder.
  5. May 19, 2026: Council authorizes the contract.
  6. July 15, 2026: Groundbreaking at 10 a.m. at George Rogers Park.
  7. September 2026: Crews finish the footings and retaining walls along the new section.
  8. October 14, 2026: Retaining wall concrete is underway, switchback concrete is scheduled, and asphalt paving is expected within weeks.

Getting the land took about sixteen years, from 2007 to 2023. Construction is scheduled to fit in one season, from a July groundbreaking to a finish the city expects in late fall.

Even during construction, the one real delay came from property. In an update posted by Old Town Lake Oswego, Parks and Recreation said a change involving a neighboring property required changes to part of the trail layout. That meant a short delay for revised plans and permits, plus some added cost, before the project got back on track. The same post asked about hard rock on the switchback. City Construction Manager Bruce Powers said crews had expected rock and silt there and built a contingency into the plan, and the area was graded without any problems.

What 870 feet of riverbank requires

The bid scope posted by NAMC Oregon lists about 877 linear feet of asphalt trail and 516 feet of retaining wall. It also calls for handrail and fencing, a French drain, tree removal, and native planting and restoration. That's more than half a foot of retaining wall for every foot of trail. The city's updates also describe a switchback, and Parks and Recreation's October note mentions paving, irrigation and landscaping along a ramp.

The Review broke down where the $1.76 million came from. The estimate includes a 20% contingency for construction costs.

Funding source

Amount

Metro local share dollars

$1,140,000

Parks system development charges

$300,000

City park development funds

$240,000

Mt. Hood Territory strategic investment grant

$80,000

Total

$1,760,000

The Metro money had other possible uses. To fund the greenway this year, the city moved $500,000 in local share funds away from a planned upgrade to the Luscher Farm driveway and parking lot.

Three parks, one continuous walk

The city says the finished path will connect Foothills Park, Roehr Park and George Rogers Park. It will also give neighborhoods south of George Rogers Park and Oswego Creek a safe walking and biking connection to downtown. Each of the three parks has its own landmarks.

George Rogers Park is a 26-acre riverfront park at 611 S. State Street, with river access, trails, athletic facilities and a large natural area. Improvements to the lower park in 2005 reopened walking access to the river and restored habitat along Oswego Creek and the Willamette. The park also holds the Oswego Iron Furnace, built in 1866 where Oswego Creek meets the Willamette. According to the Oregon Encyclopedia, it was the first iron furnace on the Pacific Coast. It's listed on the National Register, it's Oregon's oldest industrial landmark, and it's the only surviving charcoal blast furnace west of the Rocky Mountains.

Roehr Park covers 7.5 riverfront acres with viewing decks, lighted pathways, benches and an amphitheater. It also gives access to the Charlie S. Brown Water Sports Center.

Foothills Park has the Stafford Stones, which are basalt columns engraved with William Stafford's poetry. It also has a covered river-viewing platform, a timber-and-stone picnic pavilion with a fireplace, a reflecting pond and a grass amphitheater. The Lake Oswego Veterans Memorial there includes a granite wall and honor walls. In July the park hosts the city's Wednesday Concert Series.

The concerts are what the Old Town neighborhood association looks forward to most. "Next summer we'll be able to walk or ride our bikes to the outdoor summer concerts at Foothills Park!" it wrote in its October update.

The path is also part of something bigger. The Willamette River Greenway runs from Champoeg State Park in the south to where the Willamette meets the Columbia. Its major paved sections include Tom McCall Waterfront Park and the Vera Katz Eastbank Esplanade in Portland, Willamette Park and Mary S. Young Park in West Linn, and Milwaukie Bay Park.

November, with work at both ends

The new segment isn't the only riverfront work this month. The Roehr Park pathway, which links the new trail to Foothills Park, is being rebuilt too. Work started October 15. Starting October 16, crews removed the old path, leaving gravel until it's repaved, and the city expects the work to last through the end of November. Parks and Recreation says:

  • The pathway stays open for walking when construction isn't underway.
  • Intermittent closures will happen during construction and paving.
  • There may be temporary detours.
  • Posted closure signs should be followed.

That means the route between Foothills and George Rogers has construction at both ends this month. The city has also finished some smaller work at the parks. Parking lines at Roehr Park are now painted green to mark park parking, and the George Rogers Park lot has been restriped.

The city expects the new segment to be finished in late fall, with a ribbon-cutting celebration afterward. In October, Parks and Recreation told the Old Town association it expected the celebration in late November. The city's project page posts each milestone, so it's the place to check before heading out.

The downtown end of the month

The new trail's purpose is to connect the riverfront parks to downtown, and late November has several events there worth the walk.

On Saturday, November 21, the Lake Oswego Farmers' Market returns for a one-day Reunion market from 9 a.m. to 2 p.m. at Millennium Plaza Park, 200 1st Street. Its regular Saturday season ended October 31. The Reunion market brings back returning vendors, plus music, artisans and horse-drawn wagon rides.

On Friday, November 27, Millennium Plaza Park hosts the 62nd Annual Tree Lighting Festival from 3 to 7 p.m. There's a holiday marketplace, Santa photos, reindeer and local performances, and the tree is lit at 5:30 p.m.

At Lakewood Center for the Arts, Lakewood Theatre Company's Irving Berlin's White Christmas runs through December 20. Shows are generally Thursday through Saturday at 7:30 p.m. and Sunday at 2 p.m. Extra Wednesday shows are on November 18 and December 16, and Saturday matinees are on November 21 and December 5. There's no performance on November 26. If you want to spend November 21 downtown, you can do the Reunion market in the morning and the matinee in the afternoon.

Our family has followed this greenway link for a long time, from the easements to the retaining walls, and we're looking forward to seeing this stretch of riverfront connect. If you're thinking about how a new trail, a park connection or a quieter route to downtown fits the way you want to live in Lake Oswego, Wings NW Real Estate is glad to talk it through with you. Schedule a strategy call and we'll walk you through every step.

work with us

Ready to love where you might land next? Contact us!